October 8
th
, 2019
PRE-BEAM COMMISSIONING
SYSTEMS COMMISSIONING
:
Splitter magnets (David Burke and Jim Crittenden):
Elytt magnets (David Burke):
Power supplies connections
Water cooling systems – plumbing
EPICS name definitions
Hall probe testing – transfer function confirmation
Hysteresis corrections tests
4 SEPTA-1 (David Burke and
Jim Crittenden
):
Septum 1 – assembly
Septum 1 magnet measurements
Septum 1 installation (four septa) and survey
Water cooling plumbing
Power supply connections
Septum 1 hall probe testing
4 SEPTA-2 (David Burke and
Jim Crittenden
):
8 Coils production at BNL
4 Septa 2 assembly
Magnet measurements at BNL – Hall probe scan
Septa 2 installation and survey
Water cooling plumbing
Power supply connection
s
Polarity and strength test with the Hall probe
The S4 and R4 long quadrupoles (David Burke and
Jim Crittenden
):
T
wo quadrupoles assembly and survey
Power supply cable connection
Water cooling plumbing connections
One magnet shipment to BNL for magnetic measurements
Quadrupole installation and survey
Polarity and strength Hall probe testing
H5 magnets (David Burke and
Jim Crittenden
):
C-magnet magnet assembly
One magnet to be shipped to BNL and measured at SMD
Magnet installation and survey
Power supply cable connections
Water cooling
Polarity and strength Hall probe test
BPM’s (Robert Michnoff)
Cable preparation
Boards installation
EPICS names
Network
Testing
Scripts for timing the BPM system
CBETA EQUIPMENT PROTECTION System (Nilanjan Banerjee
and John Dobbins)
Completion of the review and documentation
Final pre-beam testing
Beam Arrival Monitors (BAMs) (Rob Michnoff
and John Dobbins
)
Installation
Boards at the Cornell Electronic Shop
Testing
Fast Loss Monitor system (Nilanjan Banerjee,
Rob Michnoff and John Dobbins)
Electronic boards
Installation
Cables
Hamamatsu detectors installation and testing on the floor
CBETAV (Colwyn Gulliford
and David Sagan
)
EPICS names correspondence to the model names
Time of flight and M56 adjustments
Orbit corrections (are the survey data placed into the model?) and beam position measurements scripts
Dispersion measurement scripts
Matching the Splitter lines to the FFA scripts
Orbit response scripts predictions
Main Linac Cryomodule (Peter Quigley,
Nilanjan Banerjee, Vadim Vescherevich)
Earlier Cooldown
Cryogenic control loop tuning optimization
Cavity Q0 measurements will help optimization of the load leveling
Control loops optimization under the load
Vibration sources require isolation
Acoustic piezo feedback upgrade
Wave guides upgrade
Amplifiers improvements
Laser system upgrade at the gun for different bunch patterns configurations (Adam Bartnik)
Installation of the new laser shutter.
Circular buffer tuning
Sliding Joints
in the middle of the splitter lines commissioning (
David Burke
)
Beam view screens – beam profile monitors (Karl Smolenski
and John Dobbins
)
Camera testing
Inside – outside position testing with the control system
Control system (Adam Bartnik,
Colwyn Gulliford, Kirsten Deitrick and John Dobbins
)
EPICS names
Network connections
Testing the communications
FFA - Fixed Field Alternating
Fixed Gradient correction system (
Colwyn Gulliford
, Adam Bartnik, Stephen Brooks, Nick Tsoupas)
Hall probe testing (Rob Michnoff)
Surveying by the BNL team magnet position re-check
Water cooling system check
Bunch pattern generator system (Adam Bartnik,
and Robert Michnoff
)
Testing together with the laser system
Testing the BPM response
BNL Cathode transport (Karl Smolenski and Adam Bartnik)
Dump line shielding (Karl Smolenski)
Gun and laser system commissioning (Adam Bartnik)
Injector system commissioning in September (Adam Bartnik, Kirsten Dietrick, Colwyn Gulliford, and Scott Berg)
MLC recommissioning (Nilanjan Banerjee, Peter Quigley, and Scott Berg)
This topic: CBETA
>
WebHome
>
CBETA-System-Tests
>
Pre-BeamCommissioningStatus
Topic revision:
08 Oct 2019, trbojevic