NYSERDA funding start date | 0 | 1 November 2016 | ||
1 | Engineering design documentation complete | 3 | 1st February1 | |
2 | Prototype girder assembled | 6 | End of April 2017 | |
3 | Magnet production approved | 8 | End of June 2017 | Spreader,combiner&Halbach |
4 | Beam through Main Linac Cryomodule | 10 | August | Go/no go 1 |
5 | First production hybrid magnet tested | 14 | December 2017 | |
6 | Fractional Arc Test: Beam through MLC & prototype girder | 18 | f April 2018 | Go/no go 2 |
7 | Girder production run complete | 25 | November2018 | |
8 | Final assembly and pre-beam commissioning complete | 28 | February 2019 | |
9 | Single pass beam energy scan | 32 | June 2019 | |
10 | Single pass beam with energy recovery | 36 | October 2019 | Key parameters achieved |
11 | Four pass beam with energy recovery (low current) | 38 | December 2019 | |
12 | Project complete | 42 | April 2020 | Estimate: April 2020 |