You are here: CLASSE Wiki>CBETA Web>CBETA-SponsorReports (14 Jan 2020, trbojevic)Edit Attach
Tags

Report on the NYSERDA Contract

Introduction

Contract Essential Milestones

         
         
         
         
         
         
         
         
         
         
         
         
         

  • NYSERDA funding start date

    0

    1 November 2016

    1

    Engineering design documentation complete

    3

    1st February1

    2

    Prototype girder assembled

    6

    End of April 2017

    3

    Magnet production approved

    8

    End of June 2017

    Spreader,combiner&Halbach

    4

    Beam through Main Linac Cryomodule

    10

    August

    Go/no go 1

    5

    First production hybrid magnet tested

    14

    December 2017

    6

    Fractional Arc Test: Beam through MLC & prototype girder

    18

    f April 2018

    Go/no go 2

    7

    Girder production run complete

    25

    November2018

    8

    Final assembly and pre-beam commissioning complete

    28

    February 2019

    9

    Single pass beam energy scan

    32

    June 2019

    10

    Single pass beam with energy recovery

    36

    October 2019

    Key parameters achieved

    11

    Four pass beam with energy recovery (low current)

    38

    December 2019

    12

    Project complete

    42

    April 2020

    Estimate: April 2020

Topic revision: r1 - 14 Jan 2020, trbojevic
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding CLASSE Wiki? Send feedback